PMP Exam Questions

Total 377 Questions

Last Updated Exam : 16-Dec-2024

Topic 1: Exam Pool A

An organization is embarking on the deployment of a new digital solution that will revolutionize purchasing services The project manager has created all the necessary plans and activities to ensure a successful integration and solution launch There is a risk of a partner’s system being unavailable which could impact the project negatively

What key activity is needed to ensure the project's success?


A.

Communicate to the project stakeholders that full integration may not be possible and that the project will potentially be delayed as a result.


B.

Eliminate the risk by mandating the partner to change the system settings to facilitate an easier integration with the new solution


C.

Continuously monitor the risk of the partner system's unavailability, and put the proper resolution plans in place in case the risk materializes into an actual issue


D.

Mitigate the risk by developing alternative plans to make the solution ready and available without full integration capabilities





D.
  

Mitigate the risk by developing alternative plans to make the solution ready and available without full integration capabilities



Explanation:
According to the PMBOK Guide, 6th edition, risk mitigation is one of the strategies for responding to positive or negative risks. It involves reducing the probability or impact of a risk to an acceptable level. In this case, the project manager should mitigate the risk of the partner’s system being unavailable by developing alternative plans to deliver the solution without relying on the full integration. This will help the project achieve its objectives and satisfy the customer’s needs. The other options are not the best choices because they either do not address the risk, transfer the risk to the partner, or accept the risk without taking any action.

References:
PMBOK Guide, 6th edition, page 4361
Free PMP Practice Exam Questions - 120 Sample Test Questions, Question 692

During the review of a project's list of deliverables, one of the stakeholders expressed concern that one of the requirements will not be addressed. What should the project manager do?


A.

Check the approved list of requirements to see if there are any missing items.


B.

Work with the stakeholder to improve the requirements' acceptance criteria.


C.

Review the requirements traceability matrix with the concerned stakeholder.


D.

Discuss with the stakeholder which additional requirements should be added.





C.
  

Review the requirements traceability matrix with the concerned stakeholder.



Explanation:

According to the Professional in Business Analysis (PMI-PBA)® Guide, a requirements traceability matrix is a table that links requirements to their origin and tracks them throughout the project life cycle. A requirements traceability matrix helps to ensure that all requirements are addressed by the project deliverables, and that any changes to the requirements are reflected in the project scope, schedule, cost, quality, and risk. In this scenario, the project manager should review the requirements traceability matrix with the concerned stakeholder to verify if the requirement in question is indeed missing or not. This would help to clarify the source, scope, and status of the requirement, and to identify any gaps, inconsistencies, or conflicts between the requirements and the deliverables. This would also help to avoid any misunderstandings, miscommunications, or assumptions that could lead to stakeholder dissatisfaction or project failure. Checking the approved list of requirements, working with the stakeholder to improve the acceptance criteria, or discussing additional requirements are actions that should be taken after the review of the requirements traceability matrix, not before. These actions do not address the root cause of the situation, which is the possible discrepancy between the requirements and the deliverables. 

References: (Professional in Business Analysis Reference Materials source and documents)

  • Professional in Business Analysis (PMI-PBA)® Guide, Chapter 4, Section 4.3.1.3
  • A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Seventh Edition, Chapter 5, Section 5.2.2.3
  • The Standard for Project Management – Seventh Edition, Chapter 3, Section 3.2.2.3

The client will not agree to closure, claiming that the project team has not performed the code inspections mandated in the development contract. The project team has performed the code inspections, however the records are not complete What should the project manager do?


A.

Seek expert legal advice on the interpretation of the clauses in the contract


B.

Hold a meeting with the project team project sponsor and the client to agree to the further work required to close the project and add to lessons learned


C.

Close the project and hand over the deliverables to the client


D.

Hold a lessons learned workshop with the project team and project sponsor to avoid contractual compliance issues arising in future projects





B.
  

Hold a meeting with the project team project sponsor and the client to agree to the further work required to close the project and add to lessons learned



Explanation:
According to the PMBOK Guide, project closure is the process of finalizing all activities across all of the project management process groups to formally complete the project or phase1. Project closure involves verifying that all the project deliverables have been completed and accepted by the customer or sponsor, confirming that all the contractual obligations have been met, documenting the project performance and lessons learned, releasing the project resources, and archiving the project records2.

In this question, the project manager is faced with a problem that the client will not agree to closure, claiming that the project team has not performed the code inspections mandated in the development contract. The project team has performed the code inspections, however the records are not complete. This indicates that there is a discrepancy between the contractual requirements and the project documentation, which can lead to disputes, claims, or litigation. The project manager should approach this problem by holding a meeting with the project team, project sponsor, and the client to agree to the further work required to close the project and add to lessons learned. This way, the project manager can facilitate a constructive dialogue among the key stakeholders, clarify the expectations and obligations of each party, negotiate a mutually acceptable solution, and document the agreed actions and outcomes. This will also help to maintain the relationship with the client, ensure customer satisfaction, and capture the lessons learned for future projects.

The other options are not the best actions to take to solve this problem. Seeking expert legal advice on the interpretation of the clauses in the contract is a possible option, but it should be done after trying to resolve the issue amicably with the client and the sponsor. Seeking legal advice may also escalate the conflict and damage the trust and goodwill with the client. Closing the project and handing over the deliverables to the client is not advisable, as it may violate the contract terms and expose the project to legal risks. Holding a lessons learned workshop with the project team and project sponsor to avoid contractual compliance issues arising in future projects is a good practice, but it does not address the current issue with the client and the project closure.

References:

  1. PMBOK Guide, 6th edition, p. 123
  2. PMBOK Guide, 6th edition, p. 125

A company is implementing a new system The project manager has identified that it is best to complete this project using a mix of Scrum and Kanban methodologies The product owner is confused as to how to start delivering the functionalities required.

How should the project manager assist the product owner?


A.

Coach the product owner on how to create a product backlog


B.

Encourage the team to subdivide the project tasks


C.

Create a work breakdown structure (WBS) and explain the deliverables to the product owner


D.

Discuss the product owner's responsibilities within the project team





A.
  

Coach the product owner on how to create a product backlog



Explanation:
The project manager should coach the product owner on how to create a product backlog, as this is a key artifact in Scrum and Kanban methodologies. The product backlog is a prioritized list of features, user stories, or requirements that the product owner wants to deliver in the project. The product backlog is dynamic and evolving, and it reflects the value and vision of the product. The product owner is responsible for creating, maintaining, and refining the product backlog, as well as communicating it to the development team and the stakeholders1. The project manager can assist the product owner by providing guidance, feedback, and tools on how to create a product backlog that is clear, concise, and aligned with the project goals and scope. The project manager can also help the product owner to use agile techniques, such as user story mapping, story splitting, and backlog grooming, to break down the functionalities into manageable and testable chunks, and to prioritize them based on value, risk, and dependencies2.

The other options, encouraging the team to subdivide the project tasks, creating a work breakdown structure (WBS), or discussing the product owner’s responsibilities within the project team, are not the best ways to assist the product owner. Encouraging the team to subdivide the project tasks may help the team to plan and execute the work, but it does not address the product owner’s confusion on how to start delivering the functionalities. Creating a WBS may help the project manager to define and organize the project deliverables, but it is not a suitable artifact for agile methodologies, as it is static and rigid, and does not reflect the changing needs and expectations of the customers and stakeholders3. Discussing the product owner’s responsibilities within the project team may help the product owner to understand their role and expectations, but it does not provide practical guidance on how to create a product backlog.

References: 1 A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition, Chapter 5.4.2.2 2 Agile Practice Guide, Chapter 3.2.2 3 What is a Work Breakdown Structure (WBS)? - Project Management Institute

A project manager has been assigned to lead a project to deploy a new system. The stakeholders disagree on the project objectives and approach.

What should the project manager do?


A.

Create a roles and responsibilities matrix based on the project charter and ask the sponsor to share it with all stakeholders to provide credible authority.


B.

Conduct scoping workshops with the project team to create a work breakdown structure (WBS), assign tasks to various entities share this with all stakeholders, and ask the team to complete their tasks as scheduled.


C.

Conduct a general meeting with all stakeholders and review and address a list of activities for each of them


D.

Breakdown the situation to identify the root causes for the disagreement and then work with each stakeholder and participating entity on their exact roles and responsibilities





D.
  

Breakdown the situation to identify the root causes for the disagreement and then work with each stakeholder and participating entity on their exact roles and responsibilities



Explanation

The correct answer is D. According to the PMBOK® Guide, the project manager should manage stakeholder expectations and engagement by applying appropriate tools and techniques, such as stakeholder analysis, communication management, conflict resolution, and negotiation1. The project manager should also use the project charter as a reference document to clarify the project objectives, scope, and deliverables2. By breaking down the situation and identifying the root causes for the disagreement, the project manager can address the underlying issues and concerns of each stakeholder and align them with the project vision and goals. The project manager can then work with each stakeholder and participating entity on their exact roles and responsibilities, and ensure that they are committed and supportive of the project. References: 1: PMBOK® Guide, page 513-514; 2: PMBOK® Guide, page 77-78

Development team members are located in three different time zones It is difficult to find a suitable time to hold the daily standup for all team members

What should the project manager do?


A.

Encourage frequent small team meetings with two or three team members.


B.

Give up the daily standup and replace it with a daily report


C.

Let the team members decide themselves if they want to join the meeting.


D.

Require all team members to join the daily standup regardless of the meeting time.





A.
  

Encourage frequent small team meetings with two or three team members.



Explanation:
The project manager should encourage frequent small team meetings with two or three team members to overcome the challenge of finding a suitable time for the daily standup. This is because the daily standup is an important agile practice that helps the team to coordinate their work, share progress, identify impediments, and plan the next steps. However, when the team members are located in different time zones, it can be difficult to schedule a common time that is convenient for everyone. Therefore, the project manager should facilitate smaller and more frequent meetings among the team members who are in the same or adjacent time zones, and ensure that the information is communicated and documented across the whole team. This way, the project manager can maintain the benefits of the daily standup while respecting the team members’ availability and preferences.

The other options are not correct because they do not address the issue of coordination and communication among the team members. Giving up the daily standup and replacing it with a daily report would reduce the interaction and collaboration among the team members, and might lead to delays, misunderstandings, and conflicts. Letting the team members decide themselves if they want to join the meeting would create inconsistency and confusion, and might result in some team members being left out or uninformed. Requiring all team members to join the daily standup regardless of the meeting time would impose an unfair and unrealistic burden on some team members, and might affect their motivation, productivity, and quality of work. 

References:
Agile Practice Guide, section 4.2.1, page 47, PMP Exam Prep, 10th edition, page 100

In a hybrid project, the customer decided on a major change for the project design. This change was approved and the impact on schedule and budget is known The software team leader, who is supposed to develop the software, refuses to commit to delivery dates claiming that they work using an agile approach and cannot commit to a final delivery date The hardware team depends on this software to develop their part of the product. What should the project manager do?


A.

Add this risk to the risk register and monitor it according to the risk management plan.


B.

Escalate this to higher management and ask for help to resolve the issue.


C.

Impose the delivery dates on the software team leader and notify the functional manager about the situation.


D.

Ask the software team leader to use a predictive approach and commit to a delivery date.





A.
  

Add this risk to the risk register and monitor it according to the risk management plan.



Explanation:

In a hybrid project, the project manager needs to balance the different approaches and expectations of the stakeholders and the teams. The customer’s change request may have been approved based on the assumption that the software team can deliver the software in a timely manner using an agile approach. However, the software team leader’s refusal to commit to a delivery date indicates a lack of alignment and collaboration between the teams and the customer. This creates a risk of schedule and scope deviations, as well as potential conflicts and dissatisfaction among the stakeholders. Therefore, the project manager should add this risk to the risk register and monitor it according to the risk management plan. The project manager should also communicate with the software team leader and the customer to clarify the expectations and the rationale behind the change request, and to explore possible ways to mitigate the risk and deliver the software that meets the customer’s needs and the hardware team’s dependencies. The project manager should not escalate the issue to higher management without trying to resolve it first, as this may undermine the trust and autonomy of the teams. The project manager should not impose the delivery dates on the software team leader, as this may violate the agile principles and demotivate the team. The project manager should not ask the software team leader to use a predictive approach, as this may not be feasible or suitable for the software development process and the customer’s requirements. 

References: (Professional in Business Analysis Reference Materials source and documents)

  • PMBOK® Guide, 6th edition, Section 1.2.4, p. 19
  • PMI Professional in Business Analysis (PMI-PBA)® Examination Content Outline, Domain III: Analysis, Task 5, p. 11
  • Business Analysis for Practitioners: A Practice Guide, Section 2.4.2, p. 36

A high-performing team member’s performance has been consistently increasing over the past year, leaving other peers behind The project manager has been reluctant to publicly recognize the team member’s contributions for fear of discouraging others The project manager is also concerned that the team member may leave if not rewarded for the contributions made.

What should the project manager do?


A.

Promote the higher performing team member to a higher position


B.

Request the high-performing team member to mentor the other team members


C.

Remind the high-performing team member to focus on shared rewards rather than individual rewards


D.

Reward the high-performing team member privately to avoid team disruption





B.
  

Request the high-performing team member to mentor the other team members



Explanation:

The project manager should request the high-performing team member to mentor the other team members. This is because mentoring is a way of recognizing and rewarding the team member’s expertise and contributions, as well as enhancing the skills and performance of the other team members. Mentoring can also foster a positive team culture, increase collaboration and trust, and reduce turnover and attrition. The project manager should also provide feedback and appreciation to the high-performing team member, and ensure that the mentoring process is aligned with the project objectives and expectations. The other options are not as effective or appropriate as requesting the high-performing team member to mentor the other team members.

Promoting the higher performing team member to a higher position may not be feasible or desirable, as it may create resentment among the other team members, disrupt the team dynamics, or reduce the team member’s motivation and satisfaction. Reminding the high-performing team member to focus on shared rewards rather than individual rewards may be perceived as unfair or discouraging, as it may imply that the team member’s efforts are not valued or appreciated. Rewarding the high-performing team member privately to avoid team disruption may also be seen as unfair or secretive, as it may create a sense of favoritism or inequality among the team members, and undermine the team morale and cohesion.

References: PMBOK Guide, 6th edition, Chapter 9.4.2, 9.4.3, The Benefits of Mentoring in Project Management - PMI

During the execution of a maintenance project the contractor submits an offer for additional work The project manager realizes that the activities billed are included in the initial scope of work.

What should the project manager do next in this situation?


A.

Review the project scope and negotiate with the contractor


B.

Refuse the offer as it is included in the initial project scope


C.

Review the project costs and communicate this to the project sponsor


D.

Submit a change request to approve the offer





B.
  

Refuse the offer as it is included in the initial project scope



Explanation:

According to the PMBOK Guide, the project scope is the work that needs to be accomplished to deliver a product, service, or result with the specified features and functions1. The project scope statement defines the project scope and documents the project deliverables, acceptance criteria, assumptions, and constraints2. The project manager is responsible for ensuring that the project scope is managed and controlled throughout the project life cycle3. If the contractor submits an offer for additional work that is already included in the initial project scope, the project manager should refuse the offer as it is not a valid change request and does not add any value to the project. The project manager should also communicate with the contractor to clarify the project scope and avoid any misunderstandings or conflicts. 

References:

  1. PMBOK Guide, 6th edition, p. 154
  2. PMBOK Guide, 6th edition, p. 157
  3. PMBOK Guide, 6th edition, p. 171

A project manager is tracking a project, but a key stakeholder will not accept the project's key performance indicator (KPI) results Which tool or technique should the project manager use?


A.

Autocratic decision making


B.

Expert judgment


C.

Context diagram


D.

Change control tools





C.
  

Context diagram



Explanation:

According to the PMBOK Guide, a context diagram is a visual representation of the product scope, showing a business system (process, equipment, computer system, etc.), and how people and other systems (actors) interact with it. A context diagram can help the project manager and the key stakeholder to understand the project’s key performance indicators (KPIs) and how they relate to the project objectives, scope, and deliverables. A context diagram can also help to identify the sources of data for the KPIs, the frequency of measurement, and the reporting format. A context diagram can facilitate communication and collaboration between the project manager and the key stakeholder, and help to resolve any issues or disagreements regarding the project’s KPIs. Autocratic decision making, expert judgment, and change control tools are not appropriate tools or techniques for this situation, as they do not address the root cause of the stakeholder’s dissatisfaction with the project’s KPIs, and may create more conflict or resistance.

References:
PMBOK Guide, Sixth Edition, pages 154-155, 176; PMI-PBA Guide, First Edition, pages 97-98, 102


Page 3 out of 38 Pages
Previous