PMP Exam Questions

Total 377 Questions

Last Updated Exam : 15-Apr-2025

Topic 1: Exam Pool A

Project A is critical for the company and must be completed within nine months. The project charter has been signed but the project scope statement has not been prepared Management asks the project manager to move forward with the project without an approved project scope statement.

What should the project manager do next?


A.

Escalate the issue to the project sponsor and add it to the risk register


B.

Refuse to work on the project because management is not following standard project management practices


C.

Meet with management to explain the potential problems with running a project without a project scope statement


D.

Start the project with inputs from the project charter to save time





C.
  

Meet with management to explain the potential problems with running a project without a project scope statement



According to the PMBOK Guide, 7th edition, section 5.3.1, “The project scope statement is a component of the project management plan that describes, in detail, the project’s deliverables and the work required to create those deliverables. It provides a common understanding of the project scope among project stakeholders and describes the project’s major deliverables, assumptions, and constraints.” Therefore, the project manager should meet with management to explain the potential problems with running a project without a project scope statement, such as scope creep, misalignment of expectations, poor quality, increased risks, and wasted resources. Escalating the issue to the project sponsor and adding it to the risk register (option A) may be done after meeting with management, but not before. Refusing to work on the project because management is not following standard project management practices (option B) is unprofessional and may damage the relationship with the management and the project stakeholders. Starting the project with inputs from the project charter to save time (option D) may not be feasible or effective, as the project charter is a high-level document that does not provide enough details to define and control the project scope.

During the execution phase of a healthcare IT project, stakeholders made a change request regarding user requirements There is no remaining budget available to cover that change request.

What should the project manager do next?


A.

Discuss approval of the change request in the next project meeting


B.

Perform a risk assessment on the required change request.


C.

Evaluate the change request against the project scope statement


D.

Ask the sponsor for more funds to cover the change request





C.
  

Evaluate the change request against the project scope statement



A change request is a formal document that proposes a modification to some aspect of the project, such as the user requirements, the deliverables, the schedule, the budget, or the quality standards123. Change requests can originate from various sources, such as the stakeholders, the project team, the customer, or the environment12. Change requests need to be evaluated and approved before they can be implemented, as they may have significant impacts on the project performance, scope, cost, time, quality, and risk123.

The project scope statement is a document that defines and documents the project objectives, deliverables, requirements, assumptions, constraints, and acceptance criteria12. The project scope statement is the basis for making project decisions and controlling changes12. Therefore, the project manager should evaluate the change request against the project scope statement to determine if the change is necessary, feasible, and beneficial for the project123. The project manager should also consider the impact of the change on the other project components, such as the schedule, the budget, the quality, and the risk123.

The other options are not the best actions for the project manager to take next. Discussing approval of the change request in the next project meeting (A) may delay the decision-making process and cause confusion among the project team and stakeholders. Performing a risk assessment on the required change request (B) is an important step, but it should be done after evaluating the change request against the project scope statement, as the risk assessment may depend on the scope implications of the change. Asking the sponsor for more funds to cover the change request (D) is not appropriate, as the project manager should first determine if the change is justified and aligned with the project scope statement, and then explore alternative ways to accommodate the change within the existing budget or negotiate a trade-off with the sponsor. References: 123

During daily calls team members share task progress One team member does not usually communicate many details and has critical tasks to be completed All team members are located in different countries and critical work is about to start Which two options will help the project manager in this situation? (Choose two)


A.

Encourage all team members to use a virtual workspace


B.

Ask the team to send emails with detailed task progress


C.

Talk to the team member about their engagement and take appropriate action.


D.

Reassign the work to a resource who participates in the daily calls


E.

Report the team member’s poor performance to the functional manager





A.
  

Encourage all team members to use a virtual workspace



C.
  

Talk to the team member about their engagement and take appropriate action.



A virtual workspace is a tool that allows team members to collaborate and communicate online, regardless of their physical location. A virtual workspace can help the project manager and the team to share information, documents, updates, feedback, and ideas in real time. A virtual workspace can also enhance the team’s trust, cohesion, and productivity. By encouraging all team members to use a virtual workspace, the project manager can ensure that everyone is on the same page and has access to the latest project information. The project manager can also monitor the team member’s progress and provide support if needed12.

Talking to the team member about their engagement and taking appropriate action is another option that can help the project manager in this situation. The project manager should try to understand the reasons behind the team member’s lack of communication and details, such as lack of motivation, skills, resources, or clarity. The project manager should also provide constructive feedback and guidance to the team member, and set clear expectations and goals for their performance. The project manager should also follow up with the team member regularly and recognize their achievements. If the team member does not improve their communication and details, the project manager may need to escalate the issue to the functional manager or consider reassigning the work to another resource34. References: = 12 Project Management Strategies To Improve Efficiency, Strategy 6: Use a virtual workspace; 8 Steps for Better Issue Management, Step 5: Communicate with the team; PMBOK® Guide, Sixth Edition, pages 368-369, 376-377; Agile Practice Guide, pages 28-29, 50-51.

During initiation of a new product improvement project, a project manager finds historical data showing that a similar project resulted in customers complaining of an even worse user experience compared to the previous product version.

How can the project manager prevent this outcome in the new project?


A.

Hire a team of external users to perform acceptance testing on the product.


B.

Define a user focus group as external stakeholders with a high influence on outcomes.


C.

Hire a consultant to perform a benefit analysis as an input to the project charter.


D.

Define a high-level risk and plan mitigation after completing the work breakdown structure (WBS)





B.
  

Define a user focus group as external stakeholders with a high influence on outcomes.



Explanation:
A user focus group is a group of potential or actual customers who provide feedback on a product or service. User focus groups can help project managers understand the needs, preferences, and expectations of the target market, as well as identify any problems or issues with the product or service12.

Defining a user focus group as external stakeholders with a high influence on outcomes means that the project manager recognizes the importance of involving the users in the project initiation and planning phases. By doing so, the project manager can ensure that the project aligns with the user requirements and delivers value to the customers34.

Defining a user focus group as external stakeholders also implies that the project manager will communicate with them regularly, solicit their feedback, and incorporate their suggestions into the project scope, schedule, budget, and quality5 . This can help prevent customer dissatisfaction and negative feedback, as well as increase customer loyalty and retention .

References:
1: What is a Focus Group? Definition, Examples, and Benefits
2: Focus Groups: What They Are and How to Use Them
3: Project Stakeholder Management - Project Management Institute
4: Stakeholder Analysis and Mapping: A Guide for Beginners
5: How to Manage Stakeholder Expectations in Project Management : [The Importance of Communication in Project Management] : [Customer Satisfaction: The Ultimate Guide] : [How to Increase Customer Loyalty: 5 Strategies for Success]

A large corporation is transforming itself from a predictive to agile approach A project team with knowledge of agile practices is experiencing significant conflicts with the executives regarding the processes to be followed.

How should these conflicts be resolved?


A.

Include the executives in team retrospectives


B.

Train the executives on agile practices


C.

Negotiate with the executives and agree on a process.


D.

Request that the executives use agile practices





B.
  

Train the executives on agile practices



According to the PMBOK Guide, 7th edition, one of the challenges of agile project management is to align the expectations and understanding of the stakeholders with the agile values and principles. This is especially important when the organization is transitioning from a predictive to an agile approach, as there may be resistance or confusion from the executives who are used to a different way of working. Therefore, the best way to resolve the conflicts between the project team and the executives is to train the executives on agile practices, such as iterative development, adaptive planning, customer collaboration, and continuous improvement. This will help the executives to appreciate the benefits of agile, support the project team, and provide constructive feedback. Training the executives on agile practices will also foster a culture of trust, respect, and empowerment, which are essential for agile project success. References: PMBOK Guide, 7th edition, page 14, Section 1.3.2, Agile Project Management; page 17, Section 1.4.2, Agile Mindset; page 19, Section 1.5, Agile Principles.

An organization is introducing agile to its projects. During an informal discussion the project manager learned that team members who are currently working on different teams are discussing how they would like to be together on the same team

What should the project manager do?


A.

The project manager should not allow resources to choose teams because the project manager assigns the resources based upon project needs


B.

The project manager should not allow resources to choose on which team they would like to work because they will always choose their favorite team


C.

The project manager should allow the resources to periodically choose on which team they would like to work.


D.

The project manager should indicate that the team members have already been assigned to a team through workforce optimization.





C.
  

The project manager should allow the resources to periodically choose on which team they would like to work.



Allowing the resources to periodically choose on which team they would like to work is a technique that fosters self-organization and empowerment among the team members. It also helps to create cross-functional teams that can deliver value faster and more effectively. Self-organization is one of the key principles of agile project management, as it enables the team to adapt to changing requirements and customer needs. The project manager should not prevent the resources from choosing teams, as this would undermine their autonomy and motivation. The project manager should also not assume that the resources will always choose their favorite team, as this may not be the case. The project manager should not indicate that the team members have already been assigned to a team through workforce optimization, as this would imply that the team composition is fixed and cannot be changed. References: Project Management Professional Sample Questions, page 12, question 100. [A Guide to the Project Management Body of Knowledge (PMBOK Guide)], Sixth Edition, page 52, section 2.3.2. [Agile Practice Guide], page 14, section 2.1.2.

A project manager is managing an innovation project for a big corporation The project manager is planning to use email as the main communication channel, however, the product owner prefers to use another approved communication tool instead of email

What should the project manager do?


A.

Contact the sponsor to request direction regarding the communication tool to be used by the project team


B.

Update the communications management plan based on the product owner’s preferences and distribute to the team


C.

Suggest to the team to start using the communication tool suggested by the product owner


D.

Request the product owner to use email because using another tool will increase the workload





B.
  

Update the communications management plan based on the product owner’s preferences and distribute to the team



According to the PMBOK Guide, the project manager should plan, manage, and monitor the communication activities throughout the project life cycle. The project manager should also consider the stakeholder needs, preferences, and expectations when choosing the communication methods, tools, and technologies. The project manager should also update the communications management plan as needed to reflect any changes in the communication requirements or approach. Therefore, the project manager should update the communications management plan based on the product owner’s preferences and distribute it to the team. This will ensure that the communication is effective, timely, and consistent among the project stakeholders. References: PMBOK Guide, 6th edition, pages 361-362, 368-369.

A team is holding the first demonstration of the software built to date on a medium-sized project The product owner has uncovered a number of issues they would like to be addressed before providing approval.

How should the project manager approach this problem?


A.

Plan to address the issues through backlog grooming and incorporate them into the next sprint


B.

Refer the product owner to the change management plan, then escalate to the steering committee


C.

Refer the product owner to the signed business requirement document and explain that the current plan cannot facilitate these changes


D.

Tell the product owner the issues will be addressed in the second version of the software





A.
  

Plan to address the issues through backlog grooming and incorporate them into the next sprint



According to the PMBOK Guide, backlog grooming (also known as backlog refinement) is the process of reviewing, updating, and prioritizing the product backlog items to ensure that the product backlog is ready for the next sprint1. Backlog grooming is an ongoing activity that involves collaboration between the product owner, the development team, and the project manager (or scrum master). Backlog grooming helps to clarify the requirements, remove ambiguity, identify dependencies, estimate effort, and align the product backlog with the product vision and the customer needs2.

In this question, the project manager is faced with a problem that the product owner has uncovered a number of issues that they would like to be addressed before providing approval for the software built to date. These issues may indicate that the product owner is not satisfied with the quality, functionality, or usability of the software, or that the software does not meet the acceptance criteria or the customer expectations. The project manager should approach this problem by planning to address the issues through backlog grooming and incorporating them into the next sprint. This way, the project manager can ensure that the issues are properly documented, analyzed, and prioritized, and that the development team can work on them in the next iteration. This will also help to maintain the agile principles of delivering value, satisfying the customer, and embracing change3.

The other options are not the best ways to approach this problem. Referring the product owner to the change management plan, then escalating to the steering committee is not appropriate for an agile project, as it implies a rigid and formal process that may not be responsive to the customer feedback and the changing requirements. Referring the product owner to the signed business requirement document and explaining that the current plan cannot facilitate these changes is not helpful, as it may create conflict and dissatisfaction with the product owner, and it may also indicate that the project manager is not following the agile value of responding to change over following a plan3. Telling the product owner the issues will be addressed in the second version of the software is not acceptable, as it may delay the delivery of value, compromise the quality of the product, and lose the trust of the product owner.

References: 1: PMBOK Guide, 6th edition, p. 179 2: Backlog Grooming: How to Do It and Why It Matters, ProjectManager.com, July 2020, 1 3: Manifesto for Agile Software Development, Agile Alliance, 2001, 2

A new project manager is assigned to lead an agile project The project manager wants to use motivation to encourage the team to perform well throughout the project.

What should the project manager do?


A.

Use the management reserves to fund some team-building activities


B.

Inflate project estimates to provide a financial buffer for team activities.


C.

Find another method to increase the team's performance


D.

Implement a reward system aimed to keep the team engaged and motivated





D.
  

Implement a reward system aimed to keep the team engaged and motivated



Agile project management is a flexible and iterative approach to delivering value to customers and stakeholders. Agile projects are built around motivated individuals who collaborate and communicate effectively, deliver working products frequently, and respond to changing requirements and feedback1. Motivation is a key factor that influences the performance, satisfaction, and retention of agile team members2. According to the agile manifesto, one of the principles of agile project management is to "build projects around motivated individuals. Give them the environment and support they need, and trust them to get the job done"3. Therefore, the project manager should implement a reward system that aligns with the agile values and principles, and that recognizes and reinforces the team’s achievements, contributions, and behaviors. A reward system can include both intrinsic and extrinsic rewards, such as feedback, recognition, appreciation, autonomy, mastery, purpose, growth, learning, fun, collaboration, innovation, and compensation45. A reward system should be tailored to the needs, preferences, and goals of each team member, and should be fair, transparent, and consistent. A reward system should also be flexible and adaptable, and should be reviewed and improved regularly based on the team’s feedback and performance. 

References:
What Is Agile Project Management? | A Comprehensive Guide
Motivation and Drive in Agile Teams - InfoQ
Manifesto for Agile Software Development
Motivation - the Agile Way! - Mind Tools
How can Agile leaders create and motivate effective teams?
[Rewarding Agile Teams, What are the options?]

 

A project manager is assigned to a new marketing campaign The sponsor gives the project manager an approved project management plan for review and explains the scope, business requirements, deliverables and stakeholders The project manager asks to see the project charter to gain a better understanding of the project. The sponsor says the project is small and simple so there is no need for a project charter.

What should the project manager do?


A.

Speak with peers about the need for a project charter


B.

Develop the project charter and send it for approval


C.

Explain that a project charter is necessary to ensure agreement on scope and deliverables and to define the project manager's responsibilities


D.

Agree that the project does not require a project charter, especially since the deliverables and milestones are included in the project management plan





C.
  

Explain that a project charter is necessary to ensure agreement on scope and deliverables and to define the project manager's responsibilities



A project charter is a project planning document that sells the project to stakeholders and sponsors. It provides a preliminary delineation of roles and responsibilities, outlines the project’s key goals, identifies the main stakeholders, and defines the authority of the project manager. A project charter is essential for any project, regardless of its size or complexity, as it serves the following purposes:

  • It authorizes the project and grants the project manager the permission to use organizational resources.
  • It serves as a primary sales document that summarizes the project’s value proposition and return on investment.
  • It acts as a roadmap that guides the project team and stakeholders throughout the project lifecycle.
  • It helps to manage the project scope and avoid scope creep by establishing the project boundaries and deliverables.

It facilitates communication and alignment among the project team, sponsors, and stakeholders by clarifying the project objectives, assumptions, risks, and constraints Therefore, the project manager should explain to the sponsor that a project charter is necessary to ensure agreement on scope and deliverables and to define the project manager’s responsibilities. Without a project charter, the project may face the following risks:

  • Lack of clarity and direction for the project team and stakeholders.
  • Misalignment of expectations and goals among the project team, sponsors, and stakeholders.
  • Scope creep and change requests that may impact the project schedule, budget, and quality.
  • Conflicts and disputes over roles, responsibilities, and authority.

Reduced stakeholder engagement and support References:

  • What is a Project Charter? Complete Guide & Examples
  • How to Write a Project Charter: Examples & Template Included?
  • Project charter - Wikipedia


Page 13 out of 38 Pages
Previous