PMP Exam Questions

Total 377 Questions

Last Updated Exam : 27-Dec-2024

Topic 1: Exam Pool A

The project charter was just approved and the project sponsor has given permission to proceed with the project The program manager has confirmed that one of the requested key resources is also needed on another project at the same time This will affect project delivery

What should the project manager do?


A.

Pay overtime to key resource to get the work done outside of working hours


B.

Have a meeting with project manager of the other project to find a resource optimization solution that works for both projects


C.

Speak with the client to see if the project delivery deadline can be delayed due to resource availability


D.

Talk to the program manager and about prioritizing this project over other projects so the key resources are available





B.
  

Have a meeting with project manager of the other project to find a resource optimization solution that works for both projects



The best option for the project manager in this situation is to have a meeting with the project manager of the other project to find a resource optimization solution that works for both projects. Resource optimization is a technique that aims to balance the demand and supply of resources across multiple projects and ensure that the resources are used efficiently and effectively. By meeting with the other project manager, the project manager can discuss the resource availability, requirements, constraints, and priorities of both projects and explore possible alternatives to resolve the resource conflict. Some of the alternatives may include:

Sharing the resource between the projects according to a predefined schedule or allocation percentage.
Adjusting the project schedules or activities to reduce the resource overlap or dependency.
Finding another resource with similar skills or qualifications to replace or supplement the requested resource.
Negotiating with the stakeholders to modify the project scope, quality, or budget to accommodate the resource limitation.

By collaborating with the other project manager, the project manager can find a mutually beneficial solution that minimizes the impact on both projects and maintains a good working relationship with the other project team123. References: = PMBOK® Guide, Sixth Edition, pages 318-319, 333-334; Agile Practice Guide, pages 28-29, 50-51; How to Manage Resources Across Multiple Projects.

The city has decided to build a new tram station The project will include various approaches The construction and infrastructure work will be accomplished using a predictive life cycle while software will be developed using an iterative life cycle Some neighbors are resisting the project have been asking the mayor to stop the project, and are threatening legal action

What two actions should the project manager take'? (Choose two)


A.

Discuss with the construction team alternatives on moving the new train station to another location.


B.

Publish information on the city’s website about the benefits that the new tram station will bring.


C.

Have a meeting with the mayor and explain the importance of the new train station to the city.


D.

Conduct regular meetings with the neighbors to get their buy-in for the project.


E.

Register this situation as a risk and develop a mitigation plan.





B.
  

Publish information on the city’s website about the benefits that the new tram station will bring.



E.
  

Register this situation as a risk and develop a mitigation plan.



The project manager should take two actions to deal with the situation of the neighbors resisting the project and threatening legal action. One action is to publish information on the city’s website about the benefits that the new tram station will bring, such as improved transportation, reduced traffic, increased safety, and enhanced economic development. This action can help to inform and educate the public about the project’s value proposition and address any misconceptions or concerns that the neighbors may have. The project manager can also use other communication channels, such as social media, newsletters, or press releases, to reach a wider audience and increase awareness and support for the project12.

Another action is to register this situation as a risk and develop a mitigation plan. A risk is an uncertain event or condition that can have a positive or negative effect on the project’s objectives. The situation of the neighbors opposing the project and threatening legal action is a negative risk that can potentially cause delays, cost overruns, reputation damage, or even project cancellation. The project manager should identify and document this risk in the risk register, along with its probability, impact, and priority. The project manager should also develop a mitigation plan to reduce the likelihood or severity of the risk. The mitigation plan may include actions such as engaging with the neighbors, negotiating with them, offering them compensation, or seeking legal advice34. References: = PMBOK® Guide, Sixth Edition, pages 376-377, 414-415; 8 Steps for Better Issue Management, Step 5: Communicate with the team; PMBOK® Guide, Sixth Edition, pages 395-396, 443-444; Project Risk Management - A Quick Guide, Step 3: Plan Risk Responses.

A project manager created a contingency plan associated with a risk. The risk was realized, but the client insists on using a new workaround instead The requested workaround will introduce delays and require additional budget

What should the project manager do?


A.

Request to use the management reserve to keep the schedule


B.

Mitigate risks associated with the workaround to avoid project delays


C.

Proceed with the approved risk response plan.


D.

Discuss the options with the client as part of the change control process





D.
  

Discuss the options with the client as part of the change control process



According to the PMBOK Guide, 7th edition, one of the key activities of the project manager is to engage stakeholders and manage their expectations throughout the project. This includes discussing the options with the client as part of the change control process, which is a formal and documented procedure that defines how changes to the project scope, schedule, cost, quality, or any other aspect of the project will be requested, evaluated, approved, rejected, or implemented. In this scenario, the client’s request to use a new workaround instead of the approved contingency plan is a change request that may affect the project objectives and outcomes. Therefore, the project manager should discuss the options with the client as part of the change control process, and evaluate the impact, feasibility, and benefits of the proposed workaround, as well as the implications of not following the contingency plan. Option D is the best answer for this question.

Option A is not the best answer because requesting to use the management reserve to keep the schedule is not the next thing that the project manager should do. It is a possible action that the project manager may take if the change request is approved and the project budget is insufficient to cover the additional costs of the workaround, but it is not a necessary or immediate action. Moreover, requesting to use the management reserve may not always be feasible or desirable, as it may increase the project costs and risks, and may require the approval of senior management or the project sponsor.

Option B is not the best answer because mitigating risks associated with the workaround to avoid project delays is not the next thing that the project manager should do. It is a possible action that the project manager may take if the change request is approved and the workaround introduces new or increased risks to the project, but it is not a proactive or effective action to resolve the current issue. Moreover, mitigating risks may not always be possible or sufficient, as some risks may be unavoidable or unpredictable, and may require other risk response strategies, such as avoidance, transfer, or acceptance.

Option C is not the best answer because proceeding with the approved risk response plan is not the next thing that the project manager should do. It is a possible action that the project manager may take if the change request is rejected and the contingency plan is still valid and applicable, but it is not a respectful or collaborative action to deal with the client’s request. Moreover, proceeding with the approved risk response plan may not always be appropriate or acceptable, as the client may have valid reasons or new information to suggest a different workaround, and may escalate the issue or withdraw their support if their request is ignored or dismissed. References: PMBOK Guide, 7th edition, pages 9-10, 15-16, 25-26, 35-36, 49-50, 59-60, 69-70.

During the implementation phase of a project, a new regulation affects the project, and a critical status meeting discussing the scope changes is required. The project manager discovers that a key stakeholder cannot attend the scheduled meeting

What should the project manager do?


A.

Call for a change control board (CCB) meeting, and inform the stakeholder about the outcome


B.

Update the communications management plan and implement the change


C.

Meet with the project sponsor to discuss how to address the situation.


D.

Meet with the stakeholder prior to the meeting to obtain their opinion





D.
  

Meet with the stakeholder prior to the meeting to obtain their opinion



A stakeholder is a person or group that has an interest or influence in the project, such as the sponsor, the customer, the team, the supplier, or the regulator12. A key stakeholder is a stakeholder that has a high level of power and interest in the project, and whose support and involvement are critical for the project’s success34.

A project manager is responsible for managing the expectations and communications of the stakeholders, and ensuring that their needs and requirements are met throughout the project lifecycle5 . A project manager should also involve the stakeholders in the decision-making process, especially when there are changes that affect the project scope, schedule, cost, or quality.

In this scenario, a new regulation affects the project, and a critical status meeting discussing the scope changes is required. The project manager discovers that a key stakeholder cannot attend the scheduled meeting. This means that the key stakeholder’s opinion and feedback will not be heard or considered in the meeting, which may lead to dissatisfaction, conflict, or resistance from the stakeholder later on.

Therefore, the best option for the project manager is to meet with the key stakeholder prior to the meeting to obtain their opinion. By doing so, the project manager can:

Inform the key stakeholder about the new regulation and its impact on the project.
Seek the key stakeholder’s input and suggestions on how to deal with the scope changes.
Address any concerns or issues that the key stakeholder may have.
Gain the key stakeholder’s approval and support for the proposed changes
Represent the key stakeholder’s interests and preferences in the meeting.
Communicate the outcome and action plan of the meeting to the key stakeholder after the meeting.

Meeting with the key stakeholder prior to the meeting can help the project manager to maintain a positive and collaborative relationship with the stakeholder, and to ensure that the project meets the stakeholder’s expectations and requirements. It can also help to avoid or minimize any potential risks or problems that may arise from the scope changes, such as delays, rework, disputes, or loss of trust.

References:
1: Project Stakeholder Management - Project Management Institute
2: Stakeholder Analysis and Mapping: A Guide for Beginners
3: [How to Identify Key Stakeholders in a Project]
4: [Key Stakeholders: Definition, Role & Importance]
5: [Project Communications Management - Project Management Institute] : [How to Manage Stakeholder Expectations in Project Management] : [Project Scope Management - Project Management Institute] : [How to Manage Scope Changes on a Project]

The project manager is reviewing the program risks and issues with key stakeholders One of the stakeholders wants to understand when the risk may potentially become an issue. What artifact should the project manager share with the stakeholder?


A.

Issue log


B.

Project management plan


C.

Risk management plan


D.

Risk register





D.
  

Risk register



Explanation
The risk register is an artifact that records the identified risks, their probability and impact, their status, and their response plans. It also tracks the risk triggers, which are the indicators or warning signs that a risk is about to occur. By sharing the risk register with the stakeholder, the project manager can show when a risk may potentially become an issue, based on the risk triggers and the risk status. The risk register also helps the project manager and the stakeholder to monitor and control the risks and their impacts throughout the project life cycle. 

References:
The PMI Guide to Business Analysis Includes The Standard for Business Analysis, Chapter 4: Business Analysis Planning and Monitoring, Section 4.3.4: Plan Risk Management
Business Analysis for Practitioners: A Practice Guide, Chapter 4: Planning the Business Analysis Approach, Section 4.6: Risk Management Plan
Business Analysis Techniques: 72 Essential Tools For Success, Chapter 6: Business Analysis Planning and Monitoring, Section 6.6: Risk Analysis and Management
Seven Steps to Mastering Business Analysis, Chapter 7: Requirements Analysis, Section 7.4: Risk Analysis

A project manager is managing a hybrid project After attending an iteration review, a stakeholder tells the project manager that they are very busy and asks why these reviews are held so frequently.

How should the project manager respond'?


A.

Negotiate a reduced review attendance with the stakeholder and update the stakeholder engagement plan to reflect this reduced attendance


B.

Discuss with the stakeholder the benefits of the hybrid project and how frequent reviews lead to greater value and less rework


C.

Record the issue in the issue log and escalate the conflict to the project sponsor for assistance


D.

Explain to the stakeholder that the stakeholder engagement plan requires their attendance at all reviews





B.
  

Discuss with the stakeholder the benefits of the hybrid project and how frequent reviews lead to greater value and less rework



A hybrid project management methodology is a combination of two or more different approaches to delivering projects, such as waterfall and agile1. Hybrid projects can offer benefits such as flexibility, adaptability, customer satisfaction, and innovation2. However, hybrid projects also require frequent reviews and feedback loops to ensure alignment, collaboration, and quality among the project team and stakeholders3. Therefore, the project manager should explain to the stakeholder the value of attending the iteration reviews, which are opportunities to inspect the project deliverables, provide feedback, identify issues, and plan for the next iteration4. By doing so, the project manager can demonstrate how the stakeholder’s involvement can contribute to the project success and avoid potential rework or waste.

References:
Ultimate Guide To Hybrid Project Methodologies & How To Make Them
Hybrid project management – the key to a successful future? - APM 
Hybrid project management – a systematic literature review…
TOWARDS A HYBRID PROJECT MANAGEMENT FRAMEWORK: A SYSTEMATIC LITERATURE…

A project in the execution phase is behind schedule and is missing some materials The contractor submits an offer to supply the missing materials and reimburse the cost since the internal procurement process will cause more delay The project manager does not agree with the costs submitted by the contractor for the missing materials

What should the project manager do next?


A.

Ask the project sponsor to allocate more budget to cover the costs


B.

Update the procurement management plan and negotiate with the contractor


C.

Ask the contractor to review the offer and reduce the costs.


D.

Update the procurement strategy and negotiate with the contractor





B.
  

Update the procurement management plan and negotiate with the contractor



D.
  

Update the procurement strategy and negotiate with the contractor



According to the PMBOK Guide, 7th edition, one of the project manager’s responsibilities is to develop the project team, which includes enhancing their competencies and interactions1. This can be done through various methods, such as training, coaching, mentoring, knowledge sharing, and feedback1. In this scenario, the project manager notices that only one team member has a technical skill that is essential for the product quality and schedule. This creates a risk of dependency, delay, and error. To prevent the team from being unqualified, the project manager should take two actions:

Encourage working in pairs and knowledge sharing: This is a form of informal training that allows the team members to learn from each other and transfer the technical skill. It also fosters collaboration, communication, and trust among the team members12.

Facilitate a training event with an external trainer: This is a form of formal training that provides the team members with a structured and standardized learning experience. It also ensures that the team members acquire the technical skill from a qualified and experienced source13.

These two actions will help the project manager develop the project team’s competencies and performance, as well as mitigate the risk of quality and schedule issues.

References:
PMBOK Guide, 7th edition, Chapter 9: Team Development
PMP Exam Prep, 11th edition, by Rita Mulcahy, Chapter 9: Resource Management, page 357
Professional in Business Analysis (PMI-PBA) Handbook, page 23

According to the Project Management Professional (PMP)® Guide, the procurement management plan is a document that describes how the project will acquire goods and services from external sources. It includes the procurement strategy, the contract types, the procurement roles and responsibilities, the procurement documents, the procurement process, and the change control process. The procurement management plan should be updated whenever there are changes in the project scope, schedule, budget, quality, or risks that affect the procurement activities. In this case, the project manager should update the procurement management plan to reflect the current situation of the project and the contractor’s offer. Then, the project manager should negotiate with the contractor to reach a mutually acceptable agreement on the costs, terms, and conditions of the contract. Negotiation is a technique that involves communication, problem-solving, and decision-making to resolve conflicts and disputes between parties. Negotiation can help the project manager and the contractor to achieve a win-win outcome that satisfies both their interests and objectives. Negotiation can also help to maintain a positive and collaborative relationship between the project manager and the contractor, which is essential for the successful completion of the project. References:

1: Project Procurement Management - PMI
2: Procurement Management Plan Template - Project Management Docs
3: Negotiation - PMI
4: Negotiation Skills for Project Managers - ProjectManager

A large multi-year project requires highly skilled staff for successful deployment The management team and the project sponsor have analyzed the resource requirements and agreed to have permanent staff hired for the project to avoid potential budget overrun However there is a risk of staff turnover during the course of the project, which may have an impact on the delivery.

Which two actions should the project manager take to mitigate this risk? (Choose two)


A.

Introduce a recognition program to motivate and reward resource performance


B.

Enhance the competencies of the project team through training, mentoring and coaching


C.

Increase the trained staff to create back-up for resources


D.

Meet with management to discuss dividing the project into smaller projects


E.

Convince senior management to hire third-party staff





A.
  

Introduce a recognition program to motivate and reward resource performance



B.
  

Enhance the competencies of the project team through training, mentoring and coaching



These two actions can help mitigate the risk of staff turnover during the course of a large multi-year project, because they can increase the satisfaction, motivation, and loyalty of the project team members. A recognition program can show appreciation and gratitude for the team members’ efforts and achievements, and provide positive reinforcement for their desired behavior. Training, mentoring and coaching can improve the skills and performance of the team members, and provide them with opportunities for learning and growth. These actions can also foster a positive and collaborative team culture, and enhance the trust and communication between the project manager and the team members. The other options are not effective actions to mitigate the risk of staff turnover, because they may not address the root causes or consequences of the risk, or they may create more problems or risks. Increasing the trained staff to create back-up for resources may not be feasible or

cost-effective, and it may create redundancy, confusion, or conflict among the team members. Meeting with management to discuss dividing the project into smaller projects may not be possible or desirable, and it may affect the scope, quality, or benefits of the project. Convincing senior management to hire third-party staff may not be beneficial or reliable, and it may increase the complexity and risk of the project. References: Positive Reinforcement | PMI - Project Management Institute, [The Mindful Project Manager’s Guide To Team Motivation: 11 … - Planio].

A new project manager is planning an information security project for a company that resides in different countries. What is the first step the project manager should take to gather customer requirements?


A.

Conduct a stakeholder analysis to identify how regional policies may influence needs


B.

Request relevant stakeholders to conduct an analysis and reach consensus independently


C.

Conduct a project scope review workshop with relevant stakeholders.


D.

Conduct project planning meetings in one location with relevant stakeholders





A.
  

Conduct a stakeholder analysis to identify how regional policies may influence needs



The first step the project manager should take to gather customer requirements for an information security project is to conduct a stakeholder analysis. A stakeholder analysis is a technique that helps identify the key stakeholders, their needs, expectations, interests, and influence on the project. By conducting a stakeholder analysis, the project manager can understand how regional policies may affect the customer requirements, such as legal, regulatory, cultural, or ethical factors. A stakeholder analysis can also help the project manager prioritize the requirements and plan the communication and engagement strategies with the stakeholders. References: = PMBOK® Guide, Sixth Edition, pages 513-515; A 6-step guide to requirements gathering for project success, Step 1: Assign roles.

The marketing team is transitioning to using hybrid approaches for their projects. The marketing director is not knowledgeable about hybrid methodologies and the project manager needs the director’s support as the marketing director is a key stakeholder.

What should the project manager do to obtain the support?


A.

Ask the marketing director to participate in daily meetings


B.

Mentor the marketing director on hybrid approaches


C.

Ask the marketing team members to coach the director


D.

Tram the marketing team and keep the director informed





B.
  

Mentor the marketing director on hybrid approaches



According to the PMBOK® Guide 7th Edition, one of the principles of project management is to “tailor based on context”. This means that the project manager should adapt the project delivery approach to the specific needs and characteristics of the project, the organization, and the stakeholders. Hybrid approaches are a way of combining predictive and adaptive methods to suit the project context and deliver value. The marketing director, as a key stakeholder, needs to understand and support the hybrid approach chosen by the project manager and the team. Therefore, the best option is for the project manager to mentor the marketing director on hybrid approaches, explaining the benefits, challenges, and best practices of using them. This will help the director to appreciate the value of the hybrid approach and provide the necessary guidance and resources to the project. The other options are not as effective because they do not address the knowledge gap of the director and may create resistance or confusion. Asking the director to participate in daily meetings may be too overwhelming and time-consuming for the director, and may not provide enough information or context on the hybrid approach. Asking the team members to coach the director may create role confusion and undermine the authority and credibility of the project manager. Training the team and keeping the director informed may not be sufficient to gain the director’s support and involvement, and may create a disconnect between the team and the director. References: : PMBOK® Guide 7th Edition, PMI, 2021, p. 9 : Agile Practice Guide, PMI, 2017, pp. 27-28


Page 10 out of 38 Pages
Previous