Which type of estimate refers to estimating a story based on its relationship to one or more
other stories?
A.
Algorithmic
B.
Computational
C.
Triangulating
D.
Rules of Thumb
Algorithmic
An organization adopts Agile practices and implements an incremental delivery strategy. If
implemented correctly, the company should recognize improved:
A.
procurement processes by requiring vendors to ship materials as needed.
B.
project cost management by making incremental payments on contracts.
C.
customer satisfaction by specifying project shipping dates in the contract.
D.
project Return on Investment (ROI) by releasing individual features to market.
project Return on Investment (ROI) by releasing individual features to market.
When using Agile Earned Value Management (EVM), progress should be measured at
which level?
A.
Task
B.
Iteration
C.
Product
D.
Release
Release
Which of the following is part of the 12 practices defined in eXtreme Programming (XP)?
A.
Risk management
B.
Small releases
C.
Project management
D.
Project charter
Small releases
Which of the following is a list of capabilities, features, and stories that the Product Owner
has identified?
A.
Burndown chart
B.
Story card
C.
Vision document
D.
Backlog
Backlog
When are acceptance tests typically written for a user story?
A.
After coding the story, but before user acceptance testing begins
B.
After writing the story, but before coding begins
C.
At the start of Product Backlog prioritization planning
D.
After estimating the Product Backlog, but before Sprint planning begins
At the start of Product Backlog prioritization planning
Velocity is the:
A.
total number of Product Backlog hours completed in an iteration divided by the number
of developers.
B.
measured rate at which teams turn Product Backlog items into running, tested features.
C.
measured rate at which the project manager turns the Product Backlog into tested
features.
D.
total number of Product Backlog hours completed when developers work in pairs.
measured rate at which teams turn Product Backlog items into running, tested features.
A development team has finished identifying the tasks they will be accountable for during
the next sprint. Which of the following tools best provides transparency into the progress
throughout the sprint?
A.
Burndown chart
B.
Gantt chart
C.
Hours expended chart
D.
Management baseline chart
Burndown chart
Following chart lists stories for a release of an Agile project;
If the team completes Story A, Story B, and 50% of Story C for the first iteration, what is the team's velocity?
A.
9
B.
10
C.
12
D.
15
9
Which of the following would be most likely to assist when a customer has difficulty
prioritizing stories?
A.
Split the stories into smaller ones to allow the customer to choose the pieces that they
want.
B.
Have the team provide guidance into where their priorities lie to the customer.
C.
Provide additional technical details to give the customer insight into technical
challenges.
D.
Have the team rewrite the stories with additional details to clarify requirements.
Split the stories into smaller ones to allow the customer to choose the pieces that they
want.