Topic 1: Scenario 1 "Medical Domain"
Within the projects, a master test plan and phase test plan will be used. Following is a list
of characteristics applicable for test plans:
a. Any deviation from the procedures described in the test
b. strategy document
c. The overall estimated costs, timescales and resource
d. requirements
e. A detailed schedule of testing activities
f. The development deliverables to be tested
g. Which test staff members (names) will be involved and when
h. Level of requirements coverage achieved
Which TWO of the above mentioned characteristics relate to the phase test plan? 1 credit
A.
a
B.
b
C.
c
D.
d
E.
e
F.
f
c
e
Within the projects, a master test plan and phase test plan will be used. Following is a list
of characteristics applicable for test plans:
a. Any deviation from the procedures described in the test strategy document
b. The overall estimated costs, timescales and resource requirements
c. A detailed schedule of testing activities
d. The development deliverables to be tested
e. Which test staff members (names) will be involved and when
f. Level of requirements coverage achieved
Which THREE of the above mentioned characteristics relate to the master test plan? 1
credit
A.
a
B.
b
C.
c
D.
d
E.
e
F.
f
a
b
d
The development manager is managing the review of the responses received from bidders,
and has asked the in-house test manager to provide a review checklist for the test
management aspects of the responses. Which of the following checkpoints would be
appropriate? 2 credits
A.
The bidder’s test policy should enforce that incident management fully conforms to IEEE
1044.
B.
The bidder’s project strategy shows that the data content of all the test environments
conforms to EU standards.
C.
The bidder’s test plan shows that the application will be delivered for acceptance in six
months time.
D.
The bidder’s project test plan depicts a phased implementation with later delivery dates
to be confirmed and states that test deliverables will be developed using IEEE 829 as a
Question No : 54 - (Topic 16)
29
The bidder’s project test plan depicts a phased implementation with later delivery dates
to be confirmed and states that test deliverables will be developed using IEEE 829 as a
Question No : 54 - (Topic 16)
29
Which of the following product risks would be most effectively addressed just by static
testing? 3 credits
A.
In the delivered application, one of the countries, as specified in the requirements, has
not been correctly implemented.
B.
The application takes too long to process a request for additional cover.
C.
The test cases do not cover the key requirements.
D.
The successful bidder may not deliver all the required functionality on time.
The test cases do not cover the key requirements.
Which one of the following estimation approaches is appropriate at this stage of the
project? 2 credits
A.
Create an estimate based on the function point analysis technique and test point
analysis
B.
Create an estimate based on the complexity of the code
C.
Create an estimate based on the credentials of the successful bidder
D.
Create an estimate based on a percentage of the development effort
Create an estimate based on the function point analysis technique and test point
analysis
Why might a RAD approach be a better option for the test manager rather than a
sequential development? 2 credits
A.
It will extend the development team’s abilities and enhance future delivery capabilities.
B.
It will allow the marketing, clerical and testing staff to validate and verify the early screen
prototypes.
C.
Time-box constraints will guarantee code releases are delivered on schedule.
D.
More time can be spent on test execution as less formal documentation is required.
It will allow the marketing, clerical and testing staff to validate and verify the early screen
prototypes.
Which of the following is NOT a typical key challenge for testing in a RAD based
development approach? 1 credit
A.
Re-usable test scripts for (automated) regression testing
B.
Project management and control
C.
No complete requirements specification
D.
Time-boxing
Project management and control
The business has asked for a weekly progress report. Which of the following would be
appropriate as a measure of test coverage? 2 credits
A.
Percentage of business requirements exercised
B.
Percentage of planned hours worked this week
C.
Percentage of countries that have test scenarios
D.
Percentage of test iterations completed
Percentage of business requirements exercised
As a result of the RAD based development approach, the test manager has decided to
change the risk mitigation approach. Which test technique might be most appropriate to
use? 2 credits
A.
Decision Table Testing
B.
Boundary Value Analysis
C.
Error Guessing
D.
Exploratory Testing
Exploratory Testing
Regarding the process described above, what is the most important recommendation you
would make using IEEE 1044 as a guide? 2 credits
A.
No priority or severity assigned
B.
Incident numbering is manual rather than automated
C.
No mentioning of reproduceability
D.
No classification on type of incident
No priority or severity assigned