What is the primary responsibility of the Scrum Master?
A.
To Prioritize the Product Backlog
B.
To remove any impediments the Development Team encounters during their work
C.
To work with the Product Owner to develop the Product Backlog
D.
To manage the Development Team
To remove any impediments the Development Team encounters during their work
Which of the following might the Scrum Team discuss during a Sprint Retrospective?
A.
Methods of communication
B.
The way the Scrum Team does Sprint Planning
C.
Skills needed to improve the Development Team's ability to deliver
D.
Its Definition of Done
E.
All of the above
All of the above
Which of the following is not a Scrum artifact?
Qual dos seguintes não é um artefato Scrum?
A.
User Stories
B.
Sprint Backlog
C.
Product Backlog
D.
Incremento de Software
User Stories
Which three questions are answered by all Development Team members at the Daily
Scrum?
A.
What work am I going to do today?
B.
Why were you late?
C.
What impediments are in the way of my accomplishing my work?
D.
What work did I do yesterday?
E.
How is the Sprint proceeding?
What work am I going to do today?
What impediments are in the way of my accomplishing my work?
What work did I do yesterday?
The Sprint planning meeting is comprised of how many sections?
A.
4
B.
3
C.
2
D.
1
2
You are the new Scrum Master at a company currently doing RUP in three month
iterations. Your current taskin switching from RUP to Scrum is to define how long the Sprint
cycle should be. In what units of time shouldyou define the sprint cycle?
A.
A fixed amount of months
B.
A fixed amount of weeks, excluding holidays
C.
A fixed amount of days
D.
A fixed amount of hours
A fixed amount of days
Which of the following is not reflected in a Sprint Burndown Chart?
A.
Total Days in Sprint
B.
Number of Tasks Remaining
C.
Day of Sprint
D.
Work Hours Remaining
Number of Tasks Remaining
Which of the following is a role in the Scrum framework?
A.
Database Admin
B.
Development Team
C.
QA Tester
D.
Senior Developer
Development Team
The Sprint Backlog is owned by?
A.
The Scrum Master
B.
The Product Owner
C.
The Development Team
D.
The Scrum Master and Development Team
The Development Team
Why does Scrum prevent Product Owners from changing Product Backlog items that are
being worked on during the Sprint?
A.
The development team cannot meet their Sprint commitment to complete work if
requirements are changing
B.
A Sprint cycle is not enough time for senior management review and approve changes
C.
This forces Product Owners to focus on what is really important for the team to develop.
D.
The development team must be able to limit the Product Owner authority
This forces Product Owners to focus on what is really important for the team to develop.
Page 2 out of 9 Pages |
Previous |