Which objectives are covered as part of Sprint Planning?
A.
Understanding what functionality the Product Owner desires within the next Sprint and
figuring out how to doit.
B.
Updating the scope of the release with all Sprints, end dates, and costs
C.
Reviewing current functionality that binds the software solution
D.
Recalculating empirical velocity, adjusting team capacity accordingly, and projecting end
dates
Understanding what functionality the Product Owner desires within the next Sprint and
figuring out how to doit.
The most encouraged time of day to hold a Scrum Daily Meeting is:
A.
A beginning of the day
B.
Immediately after lunch
C.
4:30 PM
D.
7:00 PM
A beginning of the day
Who defines the Sprint Backlog scope?
A.
Product Owner
B.
Development Team
C.
Scrum Master
D.
Stakeholders
Development Team
What is the recommended size for a Development Team?
A.
6, +3 or -3
B.
9
C.
6
D.
7, +2 or -2
6, +3 or -3
Upon what type of process control is Scrum based?
A.
Hybrid
B.
Defined
C.
Complex
D.
Empirical
Empirical
A _____________________ is created during the first half of the Sprint planning meeting
and a
_________________ is created during the second half of the Sprint planning meeting?
A.
Sprint Backlog, collection of tasks
B.
Product Backlog, collection of tasks
C.
Sprint Goal, Sprint Backlog
D.
Product Backlog, Sprint Backlog
Sprint Backlog, collection of tasks
Who determines whether the development team has been assigned enough work in a
Sprint?
A.
The Development Team
B.
The Product Owner
C.
The Product Owner and the Scrum Master
D.
The Scrum Master
The Development Team
From the activities given, which is the latest step in sequence of the Scrum framework?
A.
Daily scrum
B.
Sprint retrospective
C.
Sprint review
D.
Sprint planning
Sprint retrospective
When many Scrum Teams are working on a project, what best describes the definition of
"done"?
A.
All teams must use the same definition
B.
Each Team defines and uses its own
C.
Each Team uses its own but must make it clear to all other Teams
D.
It depends
All teams must use the same definition
The Sprint Goal is selected before the Sprint Backlog is created.
A.
True
B.
False
True
Page 1 out of 9 Pages |