Which tool or technique is used to manage change requests and the resulting decisions?


A.

Change control tools


B.

Expert judgment


C.

Delphi technique


D.

Change log





A.
  

Change control tools



The planned work contained in the lowest level of work breakdown structure (WBS) components is
known as:


A.

Work packages.


B.

Accepted deliverables.


C.

The WBS dictionary.


D.

The scope baseline.





A.
  

Work packages.



In which Knowledge Area is the project charter developed?


A.

Project Cost Management


B.

Project Scope Management


C.

Project Time Management


D.

Project Integration Management





D.
  

Project Integration Management



The ability to influence cost is greatest during which stages of the project?


A.

Early


B.

Middle


C.

Late


D.

Completion





A.
  

Early



Which process involves developing an approximation of the monetary resources needed to
complete project activities?


A.

Estimate Costs


B.

Control Costs


C.

Determine Budget


D.

Plan Cost Management





A.
  

Estimate Costs



Which tool or technique is used in the Develop Project Management Plan process?


A.

Pareto diagram


B.

Performance reporting


C.

SWOT analysis


D.

Expert judgment





D.
  

Expert judgment



Lessons learned are created and project resources are released in which Process Group?


A.

Planning


B.

Executing


C.

 Closing


D.

 Initiating





C.
  

 Closing



When should quality planning be performed?


A.

While developing the project charter


B.

In parallel with the other planning processes


C.

As part of a detailed risk analysis


D.

As a separate step from the other planning processes





B.
  

In parallel with the other planning processes



A key benefit of the Manage Communications process is that it enables:


A.

The best use of communication methods.


B.

An efficient and effective communication flow.


C.

 Project costs to be reduced.


D.

The best use of communication technology.





B.
  

An efficient and effective communication flow.



The ways in which the roles and responsibilities, reporting relationships, and staffing management
will be addressed and structured within a project is described in the:


A.

Human resource management plan.



B.

Activity resource requirements.


C.

Personnel assessment tools,


D.

Multi-criteria decision analysis.





A.
  

Human resource management plan.