Topic 1, Volume A

Which process determines the risks that may affect the project and documents their
characteristics?


A.

Control Risks


B.

Plan Risk Management


C.

Plan Risk Responses


D.

Identify Risks





D.
  

Identify Risks



An example of a group decision-ma king technique is:


A.

Nominal group technique.


B.

Majority.


C.

Affinity diagram.


D.

Multi-criteria decision analysis.





B.
  

Majority.



A risk response strategy in which the project team shifts the impact of a threat, together with
ownership of the response, to a third party is called:


A.

mitigate


B.

accept


C.

transfer


D.

avoid





C.
  

transfer



An output of the Plan Quality Management process is:


A.

A process improvement plan,


B.

Quality control measurements.


C.

Work performance information,


D.

The project management plan





A.
  

A process improvement plan,



A project manager should document the escalation path for unresolved project risks in the:


A.

Change control plan


B.

Stakeholder register


C.

Risk log


D.

Communications management plan





D.
  

Communications management plan



Which process in Project Time Management includes reserve analysis as a tool or technique?


A.

Estimate Activity Resources


B.

Sequence Activities


C.

Estimate Activity Durations


D.

Develop Schedule





C.
  

Estimate Activity Durations



Which risk management strategy seeks to eliminate the uncertainty associated with a particular
upside risk by ensuring that the opportunity is realized?


A.

Enhance


B.

Share


C.

Exploit


D.

 Accept





C.
  

Exploit



Payback period, return on investment, internal rate of return, discounted cash flow, and net
present value are all examples of:


A.

Expert judgment.


B.

Analytical techniques.


C.

Earned value management.


D.

Group decision-making techniques.





B.
  

Analytical techniques.



The definition of when and how often the risk management processes will be performed
throughout the project life cycle is included in which risk management plan component?


A.

Timing


B.

Methodology


C.

Risk categories


D.

Budgeting





A.
  

Timing



When a backward pass is calculated from a schedule constraint that is later than the early finish
date that has been calculated during a forward pass calculation, this causes which type of total
float?


A.

Negative


B.

Zero


C.

 Positive


D.

Free





C.
  

 Positive