Which input to the Manage Stakeholder Engagement process provides guidance on how
stakeholders can best be involved in a project?
A.
Feedback analysis
B.
Stakeholder analysis
C.
Communication management plan
D.
Stakeholder management plan
Stakeholder management plan
A method of obtaining early feedback on requirements by providing a working model of the
expected product before actually building is known as:
A.
Benchmarking.
B.
Context diagrams.
C.
Brainstorming.
D.
Prototyping.
Prototyping.
Which stakeholder classification model groups stakeholders based on their level of authority and
their active involvement in the project?
A.
Power/influence grid
B.
Power/interest grid
C.
Influence/impact grid
D.
Salience model
Power/influence grid
Which Plan Schedule Management tool or technique may involve choosing strategic options to
estimate and schedule the project?
A.
Facilitation techniques
B.
Expert judgment
C.
Analytical techniques
D.
Variance analysis
Analytical techniques
The process of estimating the type and quantity of material, human resources, equipment, or
supplies required to perform each activity is known as:
A.
Collect Requirements.
B.
Conduct Procurements.
C.
Estimate Activity Durations.
D.
Estimate Activity Resources
Estimate Activity Resources
Which basic quality tool is most useful when gathering attributes data in an inspection to identify
defects?
A.
Control charts
B.
Pareto diagrams
C.
Ishikavva diagrams
D.
Checksheets
Checksheets
Which input to the Identify Stakeholders process provides information about internal or external
parties related to the project?
A.
Procurement documents
B.
Communications plan
C.
Project charter
D.
Stakeholder register
Project charter
The Identify Stakeholders process is found in which Process Group?
A.
Initiating
B.
Monitoring and Controlling
C.
Planning
D.
Executing
Initiating
An input to Develop Project Charter is a/an:
A.
Business case.
B.
Activity list.
C.
Project management plan.
D.
Cost forecast.
Business case.
Which item is a formal proposal to modify any document, deliverable, or baseline?
A.
Change request
B.
Requirements documentation
C.
Scope baseline
D.
Risk urgency assessment
Change request