CAPM Exam Questions

Total 785 Questions

Last Updated Exam : 16-Dec-2024

Topic 1, Volume A

A project manager is appointed full-time to a project and is given full-time administrative staff and
full-time project team members. This situation describes which type of organizational structure?


A.

Projectized


B.

Weak matrix


C.

Functional


D.

Balanced matrix





A.
  

Projectized



A project charter is an output of which Process Group?


A.

Executing


B.

Planning


C.

Initiating


D.

Closing





C.
  

Initiating



Which tool or technique is effective in a project in which the deliverable is not a service or result?


A.

Inspection


B.

Variance analysis


C.

Decomposition


D.

Product analysis





D.
  

Product analysis



An element of the project scope statement is:


A.

Acceptance criteria.


B.

A stakeholder list.


C.

A summary budget,


D.

High-level risks





A.
  

Acceptance criteria.



Which document describes the necessary information to determine if a project is worth the
required investment?


A.

Cost baseline


B.

Service level agreement


C.

Memorandum of understanding


D.

Business case





D.
  

Business case



Which process involves monitoring the status of the project to update the project costs and
managing changes to the cost baseline?


A.

Estimate Costs


B.

Control Costs


C.

Determine Budget


D.

Plan Cost Management





B.
  

Control Costs



Which group is formally chartered and responsible for reviewing, evaluating, approving, delaying,
or rejecting changes to the project and for recording and communicating decisions?


A.

Project team


B.

Focus group


C.

 Change control board


D.

Project stakeholders





C.
  

 Change control board



Plan Schedule Management is a process in which Knowledge Area?


A.

Project Scope Management


B.

Project Human Resource Management


C.

Project Integration Management


D.

Project Time Management





D.
  

Project Time Management



An output of the Validate Scope process is:


A.

A requirements traceability matrix.


B.

The scope management plan.


C.

Work performance reports.


D.

Change requests.





D.
  

Change requests.



The Perform Integrated Change Control process occurs in which Process Group?


A.

Initiating


B.

Executing


C.

Monitoring and Controlling


D.

Planning





C.
  

Monitoring and Controlling




Page 4 out of 79 Pages
Previous