Topic 1, Volume A
A project manager providing information to the right audience, in the right format, at the right time
is an example of which type of communication?
A.
Efficient
B.
Effective
C.
Push
D.
Pull
Effective
Scope, schedule, and cost parameters are integrated in the:
A.
Performance measurement baseline
B.
Analysis of project forecasts,
C.
Summary of changes approved in a period,
D.
Analysis of past performance.
Performance measurement baseline
A project in which the scope, time, and cost of delivery are determined as early as possible is
following a life cycle that is:
A.
Adaptive
B.
Predictive
C.
Incremental
D.
Iterative
Predictive
What is the schedule performance index (SPI) if the planned value (PV) is $100, the actual cost
(AC) is $150, and the earned value (EV) is $50?
A.
0.50
B.
0.67
C.
1.50
D.
2.00
0.50
Which item is an input to the Define Activities process?
A.
Schedule data
B.
Activity list
C.
Risk register
D.
Scope baseline
Scope baseline
When alternative dispute resolution (ADR) is necessary, which tool or technique should be
utilized?
A.
Interactive communication
B.
Claims administration
C.
Conflict management
D.
Performance reporting
Claims administration
Which quality management and control tool is useful in visualizing parent-to-child relationships in
any decomposition hierarchy that uses a systematic set of rules that define a nesting relationship?
A.
Interrelationship digraphs
B.
Tree diagram
C.
Affinity diagram
D.
Network diagram
Tree diagram
The only Process Group that comprises processes that typically occur from the beginning to the
end of the project life cycle is:
A.
Planning.
B.
Executing,
C.
Monitoring and Controlling.
D.
Closing.
Monitoring and Controlling.
Organizational theory is a tool used in which Project Human Resource Management process?
A.
Manage Project Team
B.
Acquire Project Team
C.
Develop Project Team
D.
Plan Human Resource Management
Plan Human Resource Management
Which tools or techniques are used in the Plan Schedule Management process?
A.
Benchmarking, expert judgment, and analytical techniques
B.
Statistical sampling, benchmarking, and meetings
C.
Negotiations, pre-assignment, and multi-criteria decision analysis
D.
Expert judgment, analytical techniques, and meetings
Expert judgment, analytical techniques, and meetings