Topic 2, Volume B
The following chart contains information about the tasks in a project
A.
2,000
B.
0
C.
1,000
D.
2,000
2,000
The following chart contains information about the tasks in a project.
Based on the chart, what is the schedule performance index (5PI) for Task 4?
A.
0.83
B.
0.9
C.
1.11
D.
1.33
1.11
One of the key benefits of the Plan Human Resource Management process is that it:
A.
outlines team selection guidelines and team member responsibilities.
B.
establishes project roles and responsibilities.
C.
improves teamwork, interpersonal skills, and competencies.
D.
provides an accurate appraisal of team member performance.
establishes project roles and responsibilities.
Which Define Activities tool or technique is used for dividing and subdividing the project scope and
project deliverables into smaller, more manageable parts?
A.
Decomposition
B.
Inspection
C.
Project analysis
D.
Document analysis
Decomposition
Which type of analysis is used to determine the cause and degree of difference between the
baseline and actual performance?
A.
Schedule network analysis
B.
Reserve analysis
C.
Alternative analysis
D.
Variance analysis
Variance analysis
A projects purpose or justification, measurable project objectives and related success criteria, a
summary milestone schedule, and a summary budget are all components of which document?
A.
Work breakdown structure
B.
Requirements document
C.
Project charter
D.
Project management plan
Project charter
In the Define Activities process, the schedule management plan is used to:
A.
Capture the lessons learned from other projects for comparison.
B.
Contain the standard activity list.
C.
Document and support the project change requests.
D.
Prescribe the level of detail needed to manage the work.
Prescribe the level of detail needed to manage the work.
A project team attempts to produce a deliverable and finds that they have neither the expertise nor
the time to complete the deliverable in a timely manner. This issue could have been avoided if
they had created and followed a:
A.
risk management plan
B.
human resource management plan
C.
scope management plan
D.
procurement management plan
procurement management plan
A benefit of using virtual teams in the Acquire Project Team process is the reduction of the:
A.
cultural differences of team members
B.
possibility of communication misunderstandings
C.
costs associated with travel
D.
costs associated with technology
costs associated with travel
Those who enter into a contractual agreement to provide services necessary for a project are:
A.
buyers
B.
sellers
C.
business partners
D.
product users
sellers