Topic 2, Volume B
Project management processes ensure the:
A.
alignment with organizational strategy
B.
efficient means to achieve the project objectives
C.
performance of the project team
D.
effective flow of the project throughout its life cycle
effective flow of the project throughout its life cycle
An element of the modern quality management approach used to achieve compatibility with the
International Organization for Standardization (ISO) is known as:
A.
Forecasting,
B.
Brainstorming.
C.
Historical databases.
D.
Cost of quality.
Cost of quality.
Which items are components of a project management plan?
A.
Change management plan, process improvement plan, and scope management plan
B.
Agreements, procurement management plan, and work performance information
C.
Schedule management plan, project schedule, and resource calendars
D.
Scope baseline, project statement of work, and requirements traceability matrix
Change management plan, process improvement plan, and scope management plan
Which project document is updated in the Control Stakeholder Engagement process?
A.
Project reports
B.
Issue log
C.
Lessons learned documentation
D.
Work performance information
Issue log
A project manager should communicate to stakeholders about resolved project issues by updating
the:
A.
project records
B.
project reports
C.
stakeholder notifications
D.
stakeholder register
stakeholder notifications
Which Project Time Management process includes bottom-up estimating as a tool or technique?
A.
Estimate Activity Resources
B.
Sequence Activities
C.
Estimate Activity Durations
D.
Develop Schedule
Estimate Activity Resources
Progressively elaborating high-level information into detailed plans is performed by the:
A.
project management office
B.
portfolio manager
C.
program manager
D.
project manager
project manager
An input to the Control Quality process is:
A.
Activity attributes
B.
Quality control measurements
C.
Enterprise environmental factors
D.
Deliverables
Deliverables
The chart below is an example of a:
A.
Responsibility assignment matrix (RAM)
B.
Work breakdown structure (WBS)
C.
RACI chart
D.
Requirements traceability matrix
Requirements traceability matrix
Which Perform Quality Assurance tool or technique is used to identify a problem, discover the
underlying causes that lead to it, and develop preventative actions?
A.
Inspection
B.
Quality audits
C.
Design of experiments
D.
Root cause analysis
Root cause analysis