CAPM Exam Questions

Total 785 Questions

Last Updated Exam : 15-Apr-2025

Topic 2, Volume B

Project management processes ensure the:


A.

alignment with organizational strategy


B.

efficient means to achieve the project objectives


C.

performance of the project team


D.

effective flow of the project throughout its life cycle





D.
  

effective flow of the project throughout its life cycle



An element of the modern quality management approach used to achieve compatibility with the
International Organization for Standardization (ISO) is known as:


A.

Forecasting,


B.

Brainstorming.


C.

Historical databases.


D.

Cost of quality.





D.
  

Cost of quality.



Which items are components of a project management plan?


A.

Change management plan, process improvement plan, and scope management plan


B.

Agreements, procurement management plan, and work performance information


C.

Schedule management plan, project schedule, and resource calendars


D.

Scope baseline, project statement of work, and requirements traceability matrix





A.
  

Change management plan, process improvement plan, and scope management plan



Which project document is updated in the Control Stakeholder Engagement process?


A.

Project reports


B.

Issue log


C.

Lessons learned documentation


D.

Work performance information





B.
  

Issue log



A project manager should communicate to stakeholders about resolved project issues by updating
the:


A.

project records


B.

project reports


C.

stakeholder notifications


D.

stakeholder register





C.
  

stakeholder notifications



Which Project Time Management process includes bottom-up estimating as a tool or technique?


A.

Estimate Activity Resources


B.

Sequence Activities


C.

Estimate Activity Durations


D.

Develop Schedule





A.
  

Estimate Activity Resources



Progressively elaborating high-level information into detailed plans is performed by the:


A.

project management office


B.

portfolio manager


C.

program manager


D.

project manager





D.
  

project manager



An input to the Control Quality process is:


A.

Activity attributes


B.

Quality control measurements


C.

 Enterprise environmental factors


D.

Deliverables





D.
  

Deliverables



The chart below is an example of a:



A.

Responsibility assignment matrix (RAM)


B.

Work breakdown structure (WBS)


C.

RACI chart


D.

Requirements traceability matrix





D.
  

Requirements traceability matrix



Which Perform Quality Assurance tool or technique is used to identify a problem, discover the
underlying causes that lead to it, and develop preventative actions?


A.

Inspection


B.

Quality audits


C.

Design of experiments


D.

Root cause analysis





D.
  

Root cause analysis