Which input to the Manage Stakeholder Engagement process is used to document changes that
occur during the project?


A.

Issue log


B.

Change log


C.

Expert judgment


D.

Change requests





B.
  

Change log



An input to the Plan Stakeholder Management process is:


A.

The project charter.


B.

The stakeholder analysis.


C.

A communication management plan.


D.

A stakeholder register.





D.
  

A stakeholder register.



An input to the Plan Cost Management process is: 


A.

Cost estimates.


B.

Resource calendars,


C.

 The project charter,


D.

The risk register.





C.
  

 The project charter,



A technique used to determine the cause and degree of difference between baseline and actual
performance is:


A.

Product analysis.


B.

Variance analysis.


C.

Document analysis,


D.

Decomposition.





B.
  

Variance analysis.



The process of identifying and documenting project roles, responsibilities, required skills, and
reporting relationships and creating a staffing management plan is known as:


A.

Develop Project Team.


B.

Manage Project Team.


C.

Acquire Project Team.


D.

Plan Human Resource Management.





D.
  

Plan Human Resource Management.



Which type of dependency is legally or contractually required or inherent in the nature of work and
often involves physical limitations?


A.

Mandatory


B.

Discretionary


C.

Internal


D.

External





A.
  

Mandatory



During which process does a project manager review all prior information to ensure that all project
work is completed and that the project has met its objectives?


A.

Monitor and Control Project Work


B.

Perform Quality Assurance


C.

Close Project or Phase


D.

Control Scope





C.
  

Close Project or Phase



An input to the Manage Project Team process is:


A.

Work performance reports.


B.

Change requests.


C.

Activity resource requirements.


D.

Enterprise environmental factors





A.
  

Work performance reports.



Which input provides suppliers with a clear set of goals, requirements, and outcomes?


A.

Procurement statement of work


B.

Purchase order


C.

Source selection criteria


D.

Bidder conference





A.
  

Procurement statement of work



A large portion of a projects budget is typically expended on the processes in which Process
Group?


A.

Executing


B.

Planning


C.

Monitoring and Controlling


D.

Closing





B.
  

Planning