CAPM Exam Questions

Total 785 Questions

Last Updated Exam : 15-Apr-2025

Topic 1, Volume A

A reward can only be effective if it is:


A.

Given immediately after the project is completed.


B.

Something that is tangible.


C.

Formally given during project performance appraisals.


D.

Satisfying a need valued by the individual





D.
  

Satisfying a need valued by the individual



Project deliverables that have been completed and checked for correctness through the Control
Quality process are known as:


A.

Verified deliverables.


B.

Validated deliverables.


C.

Acceptance criteria.


D.

Activity resource requirements.





A.
  

Verified deliverables.



An output of the Perform Integrated Change Control process is:


A.

Deliverables.


B.

Validated changes.


C.

The change log.


D.

The requirements traceability matrix.





C.
  

The change log.



During which process does the project team receive bids and proposals?


A.

Conduct Procurements


B.

Plan Procurements


C.

Estimate Costs


D.

Control Budget





A.
  

Conduct Procurements



The process of monitoring the status of the project and product scope as well as managing the
changes to the scope baseline is known as:


A.

Validate Scope.


B.

Plan Scope Management.


C.

Control Scope.


D.

Define Scope.





C.
  

Control Scope.



Which output is the approved version of the time-phased project budget?


A.

Resource calendar


B.

Scope baseline


C.

Trend analysis


D.

Cost baseline





D.
  

Cost baseline



The purpose of the Project Communications Management Knowledge Area is to:


A.

Monitor and control communications throughout the entire project life cycle.


B.

Maintain an optimal flow of information among all project participants.


C.

Develop an appropriate approach for project communications.


D.

Ensure timely and appropriate collection of project information.





D.
  

Ensure timely and appropriate collection of project information.



Processes in the Initiating Process Group may be completed at the organizational level and be
outside of the project's:


A.

Level of control.


B.

Communication channels.


C.

Scope.


D.

Strategic alignment.





A.
  

Level of control.



At the completion of a project, a report is prepared that details the outcome of the research
conducted on a global trend during the project. Which item did this project create?


A.

Result


B.

Product


C.

Service


D.

 Improvement





A.
  

Result



Power, urgency, and legitimacy are attributes of which stakeholder classification model?


A.

Salience


B.

Influence/impact


C.

Power/interest


D.

Power/influence





A.
  

Salience




Page 16 out of 79 Pages
Previous