Topic 1, Volume A
Identify Risks is part of which Process Group?
A.
Planning
B.
Executing
C.
Closing
D.
Initiating
Planning
Which conflict resolution technique searches for solutions that bring some degree of satisfaction to
all parties in order to temporarily or partially resolve the conflict?
A.
Force/direct
B.
Withdraw/avoid
C.
Compromise/reconcile
D.
Collaborate/problem solve
Compromise/reconcile
Which tool or technique is used in the Perform Integrated Change Control process?
A.
Decomposition
B.
Modeling techniques
C.
Resource optimization
D.
Meetings
Meetings
A logical relationship in which a successor activity cannot start until a predecessor activity has
finished is known as:
A.
Start-to-start (SS).
B.
Start-to-finish (SF).
C.
Finish-to-start (FS).
D.
Finish-to-finish (FF).
Finish-to-start (FS).
Which type of contract gives both the seller and the buyer flexibility to deviate from performance
with financial incentives?
A.
Cost Plus Incentive Fee (CPIF)
B.
Fixed Price Incentive Fee (FPIF)
C.
Cost Pius Award Re (CPAF)
D.
Time and Material (T&M)
Fixed Price Incentive Fee (FPIF)
What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual
cost (AC) is $50, and the earned value (EV) is $25?
A.
$50
B.
$100
C.
$125
D.
$175
$125
The business needs, assumptions, and constraints and the understanding of the customers needs
and high-level requirements are documented in the:
A.
Project management plan.
B.
Project charter.
.
C.
Work breakdown structure.
D.
Stakeholder register
Project charter.
.
Which Process Group and Knowledge Area include the Sequence Activities process?
A.
Executing Process Group and Project Time Management
B.
Executing Process Group and Project Cost Management
C.
Planning Process Group and Project Time Management
D.
Planning Process Group and Project Cost Management
Planning Process Group and Project Time Management
In the Plan Stakeholder Management process, expert judgment is used to:
A.
Provide information needed to plan appropriate ways to engage project stakeholders.
B.
Ensure comprehensive identification and listing of new stakeholders.
C.
Analyze the information needed to develop the project scope statement.
D.
Decide the level of engagement of the stakeholders at each required stage.
Decide the level of engagement of the stakeholders at each required stage.
The degree, amount, or volume of risk that an organization or individual will withstand is known as
its risk:
A.
Analysis
B.
Appetite
C.
Tolerance
D.
Response
Tolerance
Page 15 out of 79 Pages |
Previous |