CAPM Exam Questions

Total 785 Questions

Last Updated Exam : 15-Apr-2025

Topic 1, Volume A

Stakeholder satisfaction should be managed as a key project:


A.

Benefit


B.

 Initiative


C.

Objective


D.

Process





C.
  

Objective



Which cost is associated with nonconformance?


A.

Liabilities


B.

 Inspections


C.

Training


D.

Equipment





A.
  

Liabilities



Which tool or technique of the Define Activities process allows for work to exist at various levels of
detail depending on where it is in the project life cycle?


A.

Historical relationships


B.

Dependency determination


C.

Bottom-up estimating


D.

Rolling wave planning





D.
  

Rolling wave planning



An output of the Create WBS process is:


A.

Scope baseline.


B.

Change requests.


C.

Accepted deliverables.


D.

Variance analysis.





A.
  

Scope baseline.



A tool or technique used in the Control Procurements process is:


A.

Expert judgment.


B.

Performance reporting.


C.

Bidder conferences.


D.

Reserve analysis.





B.
  

Performance reporting.



Configuration identification, configuration status accounting, and configuration verification and
audit are all activities in which process?


A.

Perform Quality Assurance


B.

Direct and Manage Project Work


C.

Monitor and Control Project Work


D.

Perform Integrated Change Control





D.
  

Perform Integrated Change Control



Which tool or technique is used in the Estimate Costs process?


A.

Acquisition


B.

Earned value management


C.

Vendor bid analysis


D.

Forecasting





C.
  

Vendor bid analysis



Which type of project management office (PMO) supplies templates, best practices, and training to
project teams?


A.

Supportive


B.

Directive


C.

Controlling


D.

Instructive





A.
  

Supportive



Which Define Activities output extends the description of the activity by identifying the multiple
components associated with each activity?


A.

Project document updates


B.

Activity list


C.

Activity attributes


D.

Project calendars





C.
  

Activity attributes



An input to the Identify Stakeholders process is:


A.

The project management plan.


B.

The stakeholder register.


C.

Procurement documents.


D.

Stakeholder analysis.





C.
  

Procurement documents.




Page 14 out of 79 Pages
Previous