CAPM Exam Questions

Total 785 Questions

Last Updated Exam : 15-Apr-2025

Topic 1, Volume A

Which Control Quality tool is also known as an arrow diagram?


A.

Matrix diagram


B.

Affinity diagram


C.

Tree diagram


D.

Activity network diagram





D.
  

Activity network diagram



A project manager builds consensus and overcomes obstacles by employing which
communication technique?


A.

Listening


B.

Facilitation


C.

Meeting management


D.

Presentation





B.
  

Facilitation



When does the project team determine which dependencies are discretionary?


A.

 Before the Define Activities process


B.

During the Define Activities process


C.

Before the Sequence Activities process


D.

 During the Sequence Activities process





D.
  

 During the Sequence Activities process



Typical outcomes of a project include:


A.

Products, services, and improvements.


B.

Products, programs, and services.


C.

Improvements, portfolios, and services.


D.

Improvements, processes, and products.





A.
  

Products, services, and improvements.



Which grid shows which resources are tied to work packages?


A.

Work breakdown structure (WBS)


B.

Responsibility assignment matrix (RAM)


C.

Project assignment chart


D.

Personnel assignment matrix





B.
  

Responsibility assignment matrix (RAM)



The iterative process of increasing the level of detail in a project management plan as greater
amounts of information become available is known as:


A.

Continuous improvement.


B.

Predictive planning.


C.

Progressive elaboration.


D.

Quality assurance.





C.
  

Progressive elaboration.



An effective technique for resolving conflict that incorporates multiple viewpoints from differing
perspectives to achieve consensus and commitment is:


A.

smooth/accommodate.


B.

force/direct,


C.

collaborate/problem solve,


D.

compromise/reconcile.





C.
  

collaborate/problem solve,



A temporary endeavor that creates a unique product or service is called a:


A.

Project


B.

Plan


C.

Program


D.

Portfolio





A.
  

Project



Status of deliverables, implementation status for change requests, and forecasted estimates to
complete are examples of:


A.

Earned value management.


B.

Enterprise environmental factors.


C.

Organizational process assets.


D.

 Work performance information





D.
  

 Work performance information



Which item is an output of Plan Quality Management and an input to Perform Quality Assurance?


A.

Organizational process updates


B.

 Quality metrics


C.

Change requests


D.

Quality control measurements





B.
  

 Quality metrics




Page 12 out of 79 Pages